Yesterday was Day 4 of a week-long build blitz for the Meyerhofer’s tiny house, Cilantro Poncho. Day 1 was a prep day, Day 2 we began the wall raising, and Day 3 we got all but the last panel up, so we were eager to get that last wall up yesterday.

We worked in pairs to accomplish the day’s tasks, including:

  • Bolting down the last sill plate
  • Erecting another set of scaffolding
  • Beveling & installing top plates
  • Creating a plan for beveling roof perimeter framing and testing a piece with an 8” board
  • Installing framing in door & remaining windows
  • Applying liquid flashing to rough openings (ROs)

Once we got our final sill plate bolted down that final panel slipped right into its spot so nicely it felt like it was magnetized! It was awesome to have the house finally be a box!

We were on a roll when quitting time came along so we continued working for another hour in the cooler evening air. We have two more rough openings to flash with the liquid flashing and some beveling to do for the roof perimeter framing, so that we can get our first roof panel up. I found myself dreaming about that first roof panel going up last night. It will be fun to make that dream come true!

*If you’re reading this after Cilantro Poncho's First Open House and you’d like to visit, please be sure to contact Courtney and Kurt to arrange a day and time. They can’t accept unannounced visitors because they’ve got work to do finishing their little house and they need to make sure everyone who visits can do so during a time that’s safe. Thanks!